bulgaria properties
Home arrow Tommy Blog arrow Update on Lincoln Park Construction
Update on Lincoln Park Construction PDF Print E-mail
Written by Linda O'Brien   
Friday, 11 January 2008

The National Park Service (NPS) Capitol Parks East division, notified our office that work on the sidewalk repairs at Lincoln Park, stalled recently due to contract modification issues, is progressing and is approximately 40 to 45 percent complete.  The north and south walkways leading to the Emancipation Statue have been completed as are the curbs adjacent to those walks.  In addition, the work on the steps east of the statue has been completed with the area from the steps to the statue itself expected to be completed within 2-3 days.

The contract period has been extended and is now scheduled to end on February 18, 2008, continued good weather permitting.

One person has commented on this article.
(1) Untitled
2008-03-15 04:26:38
Hmmmmmm? What is up with Lincoln Park? Nary a soul working on its repairs in weeks. Any news to report?
Written by Guest User ()
.
Name : E-mail :
Website :
Comment(s) :
J! Reactions Commenting Software
General Site License
Copyright © 2006 S. A. DeCaro
Last Updated ( Friday, 11 January 2008 )
 
< Prev   Next >